The works on preparing of the stadium in Poljud are almost completed, some of them are even already finished.
The company “Krik” from Split has completely redone all offices in the second floor that will be used by the
Local Organizing Committee of the Continental Cup and the representatives of the IAAF. After the Cup, these offices will be used by the
football club Hajduk. This is an overall space of about 500 square meters.
The works on the locker-rooms and sanitary facilities located in the ground floor of the Poljud stadium, done by the
contractor “Deltron” from Split, are also almost finished. Currently the final touches are given to the rooms and facilities in the western part of the stadium.
The main work, the new athletic track , which is installed by the
company “GMT- sport i interijeri” progresses very well and all works will be finished in a few days.
The progress of the works can be seen in our picture gallery.